New Project – Harrington Road Reconstruction

Address: Harrington Road, Harrington
Client: Midcoast Council
Value: 2.3M
Start Date: September 2017
Finish Date: January 2018
Key Components: Road Construction, Design & Construction

The Eire Constructions team have started works along a 1.27 kilometre stretch of busy Harrington Road.

As Midcoast Council’s busy roadworks schedule continues to roll out across the region, Eire Constructions will project manage the full road construction for this section and improve the existing drainage infrastructure.

The end result will raise the existing road level, reduce the intensity of a sweeping bend, and improve safety conditions for local and visiting motorists.
“This is a major project that will involve reconstructing a failed section of Harrington Road, and a realignment of the existing right hand bend,” said Ron Hartley, Mid Coast Council’s Director, Engineering and Infrastructure Services.

The works will take place from Christies Lane and continue through to approximately 300m west of Longworths Road where a new intersection will ease traffic flow. The Eire team expect to be completed in January 2018.

Valued at $2.3 million, this Harrington Road reconstruction project has been partly funded through MidCoast Council’s $30 million Roadcare Program, and is part of its commitment to improving infrastructure throughout the region.

More Hive 5 Live

Bobin Creek Road Relocation

Address: Bobin CreekClient: Mid Coast CouncilValue:$720,000Start Date: February 2019Finish Date: April 2019Key Components: Traffic Management, Road Construction, New Component, Drainage, Concrete Constructions, Key Components: Traffic Management, Road

Earth Moving and Excavation Bunnings Port Macquarie

Address: John Oxley Drive Port MacquarieClient: H. R. TroonValue:$1.25 millionStart Date: June 2018Finish Date: December 2018Key Components: Traffic Management, Road Construction, Landscaping, Drainage, Design & Construction,

Stoney Creek Sewer Rising Main Replacement

Address: Stoney Creek, North TorontoStart Date: September 2017Finish Date: November 2017Key Components: Pump Station Upgrade, Pump Station Construction, Pipeline Construction, Eire Constructions lead the way in

Maitland 14 WWPS Construction

Address: Wollombi Road, RutherfordClient: Hunter Water CorporationValue: $4.6MStart Date: January 2016Finish Date: February 2017Key Components: Sewer Bypass Management, Pump Station Upgrade, Pump Station Construction, Piling, Gravity