Address: Ocean Drive, Bonny Hills
Client: NSW Crown Holiday Parks Trust
Value: $200 K
Start Date: October 2016
Finish Date: December 2016
Key Components: Utilities Relocation, Pipeline Construction, Landscaping, Gravity Sewer Construction, Drainage, Concrete Constructions, Bulk Earthworks
One of the Mid North Coast’s most beautiful holiday parks is set to become an even more enticing place to stay thanks to improvement works and upgrades to be completed by Eire Constructions.
The improvements to the popular park, which sits atop the iconic Bonny Hills headland, will include earthworks to level previously sloping sites, installation of sandstone retaining walls and upgrades to electrical, sewer and water utilities.
The works will improve the use of previously undulating sites and will improve safety for the park’s patrons. The works commenced in late November and are set to be completed prior the busy Christmas holiday period.
Constraints include working in the confines of a small operating holiday park and ensuring works are completed within a tight construction period. Our considerate and truly collaborative approach to our works will ensure project success.