Seal Rocks Holiday Park

Address: Kinka Road, Seal Rocks
Client: NSW Crown Holiday Parks Trust
Value: 1.0 M
Start Date: June 2016
Finish Date: September 2016
Key Components: Utilities Relocation, Road Construction, Pipeline Construction, Landscaping, Gravity Sewer Construction, Electrical Installations, Drainage, Design & Construction, Concrete Constructions – Water Retaining Structures, Concrete Constructions – Pavements, Bulk Earthworks

Eire Constructions was charged with completing of contract works for the expansion of a Holiday Park at the picturesque Seal Rocks for the NSW Crown Holiday Parks Trust.

The works included the construction of new roads, retaining walls, drainage infrastructure, water and sewer utilities and electrical reticulation services for the park.

The works were completed whilst the park is still in operation, requiring a collaborative construction approach among our client, park management and patrons. The interface between all stakeholders was managed through regular planning meetings with park management and a transparent construction approach, keeping all parties up to date with the latest progress.

Another major constraint for the project included the remoteness of the site. Poor mobile reception made communication with our project management and construction team difficult to complete planning meetings, organising of resources and suppliers. This challenge was overcome by ensuring our project management had a regular presence onsite to secure the success of the project.

More Hive 5 Live

GemLife Subdivision

Client: GemLife Location: Lake Cathie, NSW Project Value: $12m Start Date: April 2021 Finish Date: Projected January 2023 Key Components: 178 lot MHE and 18 lot

Batar Creek Sewer Pump Station

Client: Land Dynamics AustraliaLocation: Kendall, NSWProject Value: $2.5mStart Date: June 2022Finish Date: December 2022Key Components: 3.6m x 7.8m deep sewer pump station and valve pit, gravity

South Kempsey Sewer

Client: Kempsey Shire CouncilLocation: South Kempsey, NSWProject Value: $3.5mStart Date: November 2021Finish Date: July 2022Key Components: 40KL commercial sewer pump station for the Puma Service Centre,

Cessnock Airport Water and Sewer

Client: Fulton HoganLocation: Wine County Drive, Pokolbin, NSWValue: $600kStart Date: February 2022Finish Date: April 2022Key Components:  Water main pipeline extension, gravity sewer pipeline extension, trenchless installation

Ocean Drive Valve Pits

Address: Cathie Road, Port MacquarieStart Date: February 2022Finish Date: TBCKey Components: Construction of three large valve pits to accommodate a three-way trunk watermain diversion. Works include