January 22, 2021

Chichester Trunk Gravity Main

Address: New England Highway, Tarro
Client: Hunter Water Corporation
Value: $4.4M
Start Date: January 2016
Finish Date: September 2016
Key Components: Pipeline Construction, Design & Construction, Bulk Earthworks

The Chichester Trunk Gravity Main (CTGM) runs for

January 22, 2021

Whipbird Grove at Lake Innes

Address: The Point Drive, Port Macquarie
Client: Private
Value :$100 K
Start Date: June 2016
Finish Date: June 2016
Key Components: Sub-divison Construction, Pipeline Construction, Gravity Sewer Construction,

‘Whipbird Grove at Innes Lake’ is a boutique 11

January 22, 2021

Bullocks Run

Address: Ocean Drive, Bonny Hills
Client: Private
Value: 2.0 M
Start Date: June 2016
Finish Date: May 2017
Key Components: Sub-divison Construction, Road Construction, Pipeline Construction, Gravity Sewer Construction, Drainage, Bulk Earthworks

When gravity sewer installation