July 20, 2025

HAZCHEM Package 3

Client:Hunter Water Corporation
Location
: Lower Hunter Region, NSW
Period: 2022-2024
Status: Completed
Project Value: $6.1M

Key Works: Wastewater leak detection system upgrades

EIRE was chosen by Hunter Water to deliver critical upgrades across multiple water and wastewater

July 20, 2025

Gordon St Rehabilitation

Client: Port Macquarie Hastings Council
Location
: Port Macquarie, NSW
Period: 2021 – 2022
Status: Completed
Project Value: $7.7M

EIRE Constructions was awarded the Gordon Street project to improve the existing under-capacity stormwater infrastructure and to improve the water

July 20, 2025

Grahamstown Treatment Plant

Client: Hunter Water Corporation
Location
: Tomago, NSW
Period: 2024
Status: Current
Project Value: $38M

Eire were awarded the Hunter Water Corporation Grahamstown Treatment Plan project aimed at enhancing the chemical delivery, storage, and dosing systems. Eire was selected

July 20, 2025

Black Hill Trunk Main Duplication

Client: Hunter Water Corporation
Location
: Blackhill, NSW
Period: 2023 – 2024
Status: Completed
Project Value: $3.9M

Key Works: Design of pipeline | Community Liaison and Communication Plan | Supply and install 2.6km of DN375 PVC | HDD boring