July 20, 2025

Black Hill Trunk Main Duplication

Client: Hunter Water Corporation
Location
: Blackhill, NSW
Period: 2023 – 2024
Status: Completed
Project Value: $3.9M

Key Works: Design of pipeline | Community Liaison and Communication Plan | Supply and install 2.6km of DN375 PVC | HDD boring

July 17, 2025

Louth Park Trunk Watermain Renewal

Client: Hunter Water
Location
: Louth Park, NSW
Period: 2024
Status: Complete
Project Value: $6.6M

Eire Constructions was engaged by Hunter Water Corporation to deliver the renewal of a critical trunk watermain in Louth Park, south of Maitland. The

June 21, 2022

Batar Creek Sewer Pump Station

Client: Land Dynamics Australia
Location
: Kendall, NSW
Project Value: $2.5m
Start Date: June 2022
Finish Date: December 2022
Key Components: 3.6m x 7.8m deep sewer pump station and valve pit, gravity sewer main from new sub-division under rail