• Project Details

    • Address:Fern Bay NSW
    • Client:Private Client
    • Value:$1.6M
    • Start Date:November 2014
    • Finish Date:March 2015

    Key Components: Trenchless Technology, Traffic Management, Road Construction, Pipeline Construction,

    Eire Constructions carried out utilities installation and road construction works for

  • Project Details

    • Address:Pacific Hwy, Bangalow
    • Client:Lend Lease Engineering
    • Value:$3.5M
    • Start Date:September 2013
    • Finish Date:May 2016

    Key Components: Road Construction, Plant Hire, Pipeline Construction, Drainage, Bulk Earthworks,

    As part of the Federal Government’s scheme to provide

  • Project Details

    • Address:Sancrox Road, Thrumster NSW
    • Client:Ferrovial Aggroman
    • Value:$3.2M
    • Start Date:July 2014
    • Finish Date:May 2016

    Key Components: Utilities Relocation, Road Construction, Plant Hire, Pipeline Construction, Drainage, Bulk Earthworks,

    Eire Constructions worked as a sub-contractor for …

  • Project Details

    • Address:New England Highway, Tarro
    • Client:Hunter Water Corporation
    • Value:$4.4M
    • Start Date:January 2016
    • Finish Date:September 2016

    Key Components: Pipeline Construction, Design & Construction, Bulk Earthworks,

    The Chichester Trunk Gravity Main (CTGM) runs for 70 kilometres …

  • Project Details

    • Address:Ocean Drive, Rainbow Beach
    • Client:Private
    • Value:$400 K
    • Start Date:May 2016
    • Finish Date:July 2016

    Key Components: Sub-divison Construction, Plant Hire, Pipeline Construction, Gravity Sewer Construction,

    Eire Constructions was engaged to complete the installation of …

  • Project Details

    • Address:The Point Drive, Port Macquarie
    • Client:Private
    • Value:$100 K
    • Start Date:June 2016
    • Finish Date:June 2016

    Key Components: Sub-divison Construction, Pipeline Construction, Gravity Sewer Construction,

    ‘Whipbird Grove at Innes Lake’ is a boutique 11 lot …

  • Project Details

    • Address:Cnr Failford Road and Bullocky Way, Failford
    • Client:Private
    • Value:2.0 M
    • Start Date:June 2016
    • Finish Date:May 2017

    Key Components: Sub-divison Construction, Road Construction, Pipeline Construction, Gravity Sewer Construction, Drainage, Bulk Earthworks,

    When gravity sewer …

  • Project Details

    • Address:Kinka Road, Seal Rocks
    • Client:NSW Crown Holiday Parks Trust
    • Value:1.0 M
    • Start Date:June 2016
    • Finish Date:September 2016

    Key Components: Utilities Relocation, Road Construction, Pipeline Construction, Landscaping, Gravity Sewer Construction, Electrical Installations, Drainage, Design …

  • Project Details

    • Address:Ocean Drive, North Haven
    • Client:Private Client
    • Value:$1.0 M
    • Start Date:August 2016
    • Finish Date:May 2017

    Key Components: Utilities Relocation, Pipeline Construction,

    Eire Constructions joined a consortium of contractors charged with completing the replacement of …