January 22, 2021

Fern Bay to Williamtown Water Main Construction

Address: Fern Bay NSWClient: Private ClientValue: $1.6MStart Date: November 2014Finish Date: March 2015Key Components: Trenchless Technology, Traffic Management, Road Construction, Pipeline Construction Eire Constructions carried out […]
January 22, 2021

Belmont 6 Rising Main Upgrade

Address: Belmont, NSWClient: Hunter Water CorporationValue: $6MStart Date: January 2015Finish Date: December 2015Key Components: Trenchless Technology, Traffic Management, Road Construction, Pipeline Construction When Hunter Water Corporation […]
May 20, 2017

New Project – Catarina Village Stage 2 Sub-division Construction

Address: Ocean Drive, Rainbow BeachClient: PrivateValue: $400 KStart Date: May 2016Finish Date: July 2016Key Components: Sub-divison Construction, Plant Hire, Pipeline Construction, Gravity Sewer Construction. Catarina Village overlooks […]
November 14, 2016

New Project – Bonny Hills Holiday Park Terrace Works

Address: Ocean Drive, Bonny HillsClient: NSW Crown Holiday Parks TrustValue: $200 KStart Date: October 2016Finish Date: December 2016Key Components: Utilities Relocation, Pipeline Construction, Landscaping, Gravity Sewer […]