Grants Head Quarry Intersection

Address: Ocean Drive, Bonny Hills NSW
Client: Hy-tec Concrete and Aggregates
Value: $700K
Start Date: December 2015
Finish Date: May 2016
Key Components: Utilities Relocation, Traffic Management, Road Construction

Eire Constructions was engaged by Hy-tec Concrete and Aggregates to construct a new intersection into the Grants Head Quarry in order to improve traffic flow and safety around the quarry entrance.

As Head Contractor, Eire constructed a right hand turning lane for trucks to enter the quarry safely, where previously they had been stopping or slowing in the live traffic lane before turning right.

The scope of the works included excavation to road foundation, installation of foundation treatments due to poor ground conditions, installation of sub-surface drainage, relocation of utilities, embankment and road pavement construction, installation of final seal and ancillary items.

As a result of these works the risk of accident has been reduced, trucks are able to navigate into the quarry easily, and there is improved safety for road users.

More Hive 5 Live

GemLife Subdivision

Client: GemLife Location: Lake Cathie, NSW Project Value: $12m Start Date: April 2021 Finish Date: Projected January 2023 Key Components: 178 lot MHE and 18 lot

Batar Creek Sewer Pump Station

Client: Land Dynamics AustraliaLocation: Kendall, NSWProject Value: $2.5mStart Date: June 2022Finish Date: December 2022Key Components: 3.6m x 7.8m deep sewer pump station and valve pit, gravity

South Kempsey Sewer

Client: Kempsey Shire CouncilLocation: South Kempsey, NSWProject Value: $3.5mStart Date: November 2021Finish Date: July 2022Key Components: 40KL commercial sewer pump station for the Puma Service Centre,

Cessnock Airport Water and Sewer

Client: Fulton HoganLocation: Wine County Drive, Pokolbin, NSWValue: $600kStart Date: February 2022Finish Date: April 2022Key Components:  Water main pipeline extension, gravity sewer pipeline extension, trenchless installation

Ocean Drive Valve Pits

Address: Cathie Road, Port MacquarieStart Date: February 2022Finish Date: TBCKey Components: Construction of three large valve pits to accommodate a three-way trunk watermain diversion. Works include