Ocean Drive Valve Pits

Address: Cathie Road, Port Macquarie
Start Date: February 2022
Finish Date: TBC
Key Components: Construction of three large valve pits to accommodate a three-way trunk watermain diversion. Works include deep excavation, installation of flanged pipework suspended through the excavation and pits, form, reinforce and pour of three large reinforced concrete pits, including forming and pouring around the pre-installed pipework.

The Ocean Drive Valve pit is an early works package for one of Port Macquarie’s largest upcoming roadworks upgrades. EIRE are re-aligning and upsizing an existing major DN450 trunk water main that currently supplies the towns to the south of Port Macquarie.

Due to the depth of the pit, careful monitoring and implementation of the excavation dewatering was necessary to maintain a safe worksite, free of deep water hazards and unstable excavations. Additionally, filtration of the dewatering process was necessary to ensure only clean water left the site during significant rainfall events.

The valves and pits constructed during this early works package enable a smoother cross-connection once the major project is complete and the new water main is ready to be commissioned.

"During planning for commencement of construction, Eire Constructions identified a discrepancy between the Client-supplied pipe & fittings and the project drawings. The project team was able to work through the information and propose a solution to the Client that involved minimal design changes. In doing so, most of the pre-order pipeworks were able to be utilised with only several additional items needing to be procured."

Early community engagement made sure close residents were kept informed of any potential disruptions, with minimal community impact.

The overall aim for these valve pits is to secure the future potable water supply to Port Macquarie and surrounds.

More Hive 5 Live

GemLife Subdivision

Client: GemLife Location: Lake Cathie, NSW Project Value: $12m Start Date: April 2021 Finish Date: Projected January 2023 Key Components: 178 lot MHE and 18 lot

Batar Creek Sewer Pump Station

Client: Land Dynamics AustraliaLocation: Kendall, NSWProject Value: $2.5mStart Date: June 2022Finish Date: December 2022Key Components: 3.6m x 7.8m deep sewer pump station and valve pit, gravity

South Kempsey Sewer

Client: Kempsey Shire CouncilLocation: South Kempsey, NSWProject Value: $3.5mStart Date: November 2021Finish Date: July 2022Key Components: 40KL commercial sewer pump station for the Puma Service Centre,

Cessnock Airport Water and Sewer

Client: Fulton HoganLocation: Wine County Drive, Pokolbin, NSWValue: $600kStart Date: February 2022Finish Date: April 2022Key Components:  Water main pipeline extension, gravity sewer pipeline extension, trenchless installation

Ocean Drive Valve Pits

Address: Cathie Road, Port MacquarieStart Date: February 2022Finish Date: TBCKey Components: Construction of three large valve pits to accommodate a three-way trunk watermain diversion. Works include